Project Information
Client: Truong Thanh Tra Vinh Wind Power Joint Stock Company
Deployed in: Duyen Hai Town, Tra Vinh Province
Dịch Vụ: Testing and Commisioning for Electrical Equipments
Immediately after completing the energizing project of Amaccao Quang Tri 1 Wind Power Plant, the construction team of Asia Electric Energy Joint Stock Company (ACEE) continued to set off with a journey down to the Southwest region with the destination, which was Tra Vinh Wind Power Plant project V1-2.

Tra Vinh Wind Power Plant V1-2, invested by Truong Thanh Group of Vietnam and Sermsang Power Corporation Public (SSP) of Thailand, was handed over to Truong Thanh Tra Vinh Wind Power Joint Stock Company to directly deploy. Tra Vinh V1-2 wind power plant has a total investment of over VND 2,232 billion, built on an area of more than 200 hectares in Truong Long Hoa commune, Duyen Hai town, Tra Vinh province. The project scale includes 12 wind turbines installed at sea, each turbine has a capacity of 4MW and the total installed capacity of the plant is 48MW. When in operation, the annual electricity output is expected to be 162.97 million kWh.
ACEE is proud to be the unit carrying out the testing and calibration of the 110kV substation for the project. Like most other projects during the outbreak of COVID-19 in the southern provinces, ACEE’s engineering team both worked hard to ensure progress and completely isolated at the project. With 200% of the energy to complete the dual goal, at 1am, September 26, 2021 The 110kV transformer station of Tra Vinh Wind Power Plant V1-2 was successfully energized, connected to the national grid safely and stably.
The successful energization of the Tra Vinh V1-2 Wind Power Plant project has an important meaning to carry out the acceptance test (AGC, PQ suction power, 72h reliable running) and recognize the Commercial Operation Date (COD) before October 31, 2021. This is considered a “golden” time for wind power plants to enjoy the preferential price mechanism according to Decision 39/2018/TTg issued on June 29, 2011 by the Prime Minister on the mechanism to support the development of wind power projects in Vietnam.
Project Overview
WATTAGE
48MW
NUMBER OF TURBINES
12
TOTAL INVESTMENT
2200B VND
TURBINE POWER
4MW
SYNCHRONIZING
10/2021
Electrical Testing Services For Buildings and Businesses
A Chau Electric Energy Joint Stock Company has been and will strive to become a leading company in electrical testing services in Vietnam, worthy of a prestigious and reliable brand.
We provide services and products to a wide range of customers in a variety of manufacturing and management sectors.

Electrical Equipment Calibration Experiment

Electrical Equipment Safety Inspection

Verification Of Measuring Instruments, Measurement Standards

Design & Consultancy For Electrical Works