Energizing the Bac Giang-Lang Son 220kV line and installing 2 Lang Son 220kV substations: Strengthening electricity security for the northern region during the hot season
At 3:36 a.m. on July 2, 2023, the Central Power Project Management Board (CPMB) coordinated with relevant units to energize the Bac Giang

Completed installation of horizontal capacitor banks of 8 220kV transformer stations, ready to ensure electricity for the Northern region from the hot season of 2024
On the morning of April 28, 2024, the Power Transmission Project Management Board (NPTPMB) completed the installation of 8/8 horizontal capacitors at the

Energize the project ready to supply electricity for testing of Nhon Trach 3 Power Plant
On the evening of May 15, 2024, the Southern Power Project Management Board coordinated with relevant units to accept and energize the 220kV Line
News

Energizing the Bac Giang-Lang Son 220kV line and installing 2 Lang Son 220kV substations: Strengthening electricity security for the northern region during the hot season
At 3:36 a.m. on July 2, 2023, the Central Power Project Management Board (CPMB) coordinated with relevant units to energize the Bac Giang

Completed installation of horizontal capacitor banks of 8 220kV transformer stations, ready to ensure electricity for the Northern region from the hot season of 2024
On the morning of April 28, 2024, the Power Transmission Project Management Board (NPTPMB) completed the installation of 8/8 horizontal capacitors at the

Energize the project ready to supply electricity for testing of Nhon Trach 3 Power Plant
On the evening of May 15, 2024, the Southern Power Project Management Board coordinated with relevant units to accept and energize the 220kV Line